Question 1
Case Facts as on March 31, 2012 
Mark Construction Company (MCC) has bagged a contract for construction of a large dam and hydro power project on river Shivna in Madhya Pradesh (MP). The project is also of relevance from the irrigation perspective due to its location and as per the agreement MCC will have to undertake construction of web of canals, approach road to dam, power house and other ancillary units. MCC is promoted by Mr. Thomas Mark, who is a MP from the ruling party which recently formed government in MP. Historically, MCC has been engaged into construction of rural roads, small bridges and railway platforms on contract basis for the Government. MCC will have a separate special purpose vehicle (SPV) floated for this venture. 
The hydro power project comes under the public private partnership scheme of the Government of MP, where in the private partner builds owns operates and transfers (BOOT) the hydro power plant. The detailed terms of the hydro power project agreement are as follows:
1. The construction of the dam, canals and hydro power plant shall be undertaken by the contractor. The Government of MP will have to acquire land which will submerge on construction of dam and shall rehabilitate the owners of land. 
2. MCC shall have right to operate the hydro power project from date of commencement of commercial operations (DCCO) for a period of 20 years and shall transfer the project to Government thereafter. Further, SPV shall be tax exempt for a period of five years from DCCO i.e. FY17-FY21. 
3. The power project is of 600 megawatts (MW) shall comprise 4 units of 150 MW each. The estimated cost of project is about INR3, 500 Million to be spent over a period of 4 year(s) the project is estimated to be commercially operational by April 1, 2016 with two units operational om same day and one unit each will be operational on April 1, 2017 and April 1, 2018. 
4. Means of finance:
  
Means of Finance INR Million 
Government Aid (To be classified as Equity) 500Equity 900 Debt 2100 
5. Amount if expenditure estimated in various years is as follows:
Funding 
Cost of ProjectINR MillionDebtGovt Aid EquityTotal 
FY13 (April to march)7000250450700 
FY1412005002504501200 
FY1512001200-1200 
FY15400400-400 
Debt shall bear a fixed rate of interest of 10% and all interest till DCCO shall be added to the principal. The expected principal along with capitalized interest is expected to be INR2, 400 Million (i.e.INR2100 Million debt plus INR300 Million capitalized interest). The repayment of the same shall be in 12 equated annual installments starting from FY17. 
Brief projections for the period of FY17 to FY21 are given below:
  
Developments as on March 31, 2015 
The project manager for the SPV made following comments at a press conferee on March 31, 2015:
As you all are aware, we were running bang on schedule till we last met on December 21, 2014. From today we are just left with one more year to complete the project in time. However, the flash floods which struck our dam site on this March 15, 2015 have created havoc in the region. I shall not point out the loss of lives in the region as you all are well aware of those. Our project has also been badly hit due to the same and we have been assessing the damage over the last one week. After analyzing damage, we have made changes in project schedule. Now we will be making only one unit of 150 MW operational on April 1, 2016 and 1 unit each will be added in each of subsequent year(s). 
Development as on September 30, 2015 
Post the flash floods, lot of environmentalists started raising issues of changes in environment due to construction of large number of dams. A few Public Interest Litigations (PILs) have been filed in various courts. 
Honorable High Court of MP on September 27, 2015, banned construction of any dams in the region and banned permissions for new dams till next hearing scheduled on November 30, 2015. MCC in its press release has indicated that they will apply to the higher court on the matter.  
As a credit rating analyst on September 30, 2015, on receipt of the high court order, what rating action you will take:
  1. Put ratings on rating watch.
  2. Change rating outlook for long term to negative.
  3. No action, wait for order if higher courts or hearing on November 30, 2015.
  4. Immediately downgrade ratings of SPV.
Correct answer: A
Question 2
Scott is a credit analyst with one of the credit rating agencies in India. He was looking in Oil and Gas Industry companies and has presented brief financials for following 4 entities:
  
Giving equal weightage to all three ratios, determine which of the above entities should be rated highest on a relative scale.
  1. C Ltd
  2. A Ltd
  3. D Ltd
  4. B Ltd
Correct answer: A
Question 3
Scott is a credit analyst with one of the credit rating agencies in India. He was looking in Oil and Gas Industry companies and has presented brief financials for following 4 entities:
  
From the data given below, calculate the standard deviation of the credit portfolio assuming that facility’s exposure is known with certainty, customer defaults and LGDs are independent of one another and LGDs are independent across borrower(s). 
Credit Facility A – Loss Equivalent Exposure of $60m, expected Default frequency of 1.5%, loss given default of 30%, Std Deviation of LGD – 5% and Correlation to portfolio – 0.10 
Credit Facility B – Loss Equivalent Exposure of $25m, expected Default frequency of 2%, loss given default of 12%, Std Deviation of LGD – 12% and Correlation to portfolio – 0.45 
Credit Facility C – Loss Equivalent Exposure of $15m, expected Default frequency of 5%, loss given default of 85%, Std Deviation of LGD – 18% and Correlation to portfolio – 0.22
  1. US$6.88 million
  2. US$ 1.16 million
  3. US$ 1.66 million
  4. US$ 0.10 million
Correct answer: B
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!