Question 1
Assume that you are the Test Manager for a small banking application development project. 
You have decided to adopt a risk-based testing strategy and 5 product risks (R1, R2, R3, R4, and R5) have been identified during the quality risk analysis. 
The following table shows the risk level associated to these product risks (higher numbers mean higher risk):
  
55 test cases have been designed and implemented to cover all these 5 product risks. The coverage is described in a traceability matrix. 
This is the test execution status table, after the after the first week of test execution:
About 56% of the planned test cases have been successfully executed. 
Assume that no additional product risks have been identified during the first week of test execution. 
  
Which of the following answers would you expect to best describe the residual risks associated with the identified product risks, at the end of the first week of test execution?
  1. Since R3 is the only risk for which all test cases have passed, the risk has been reduced by 20%
  2. The test execution status table indicates that the risk has been reduced by 56%
  3. The residual risk level can’t be determined, because it requires that all the test cases have been executed
  4. The test execution table doesn’t give an indication of the risk level of the open defects and the test cases that failed or are not run yet
Correct answer: D
Question 2
You are the Test Manager for a project to develop a client-server application that allows wine vendors to order custom-assorted packages of wines of several winemakers to sell special packages in their wine shops. 
You decide to apply a blended risk-based and reactive testing strategy. Below the exit criteria for the system testing. 
EXCR1- Each “critical” quality risk item must be covered by at least one test condition 
EXCR2- Each “critical” requirement must be covered by at least one test condition 
The following are the “critical” requirements of the application:
REQ-SEL-1. The application shall allow the user to order only one package at a time 
REQ-SEL-2. The application shall allow the user to select between four different packages (2-bottles, 6-bottles, 12-bottles, 15-bottles) 
REQ-SEL-3. The application shall allow the user to order a package containing at least 1 bottle and no more bottles than the package size. No error messages shall be displayed if the user selects a valid number of bottles (at least 1 bottle and no more than the package size) 
REQ-SEL-4. The application shall display an error message “Invalid number of bottles” if an invalid number of bottles is selected by the user (zero bottles or a number higher than the package size) 
REQ-PAY-1. The application shall allow the user to pay with the three accepted credit cards (Visa, MasterCard, American Express) 
REQ-PAY-2. The application shall display an error message “Invalid credit card” if invalid credit card data are given by the user 
The following is the unique “critical” quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to get the number of bottles from the user 
Test analysis for system testing has just begun and the following test conditions have been identified. 
TC-SEL-2. Test the selection of the package sizes 
TC-SEL-4. Test wrong numbers of bottles for an order 
TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles from the user 
Assume that you have used traceability to determine the logical test cases that cover all the requirements and the single risk item identified in that scenario. 
Which of the following is a positive logical test that is complete and correct, and covers the REQ-SEL-4 requirement?
  1. Select a 6-bottles package, then try to insert 5 bottles; verify that no error messages are displayed
  2. Select a 6-bottles package, then try to insert 7 bottles; verify that no error messages are displayed
  3. Select a 6-bottles package, then try to insert 7 bottles; verify that the "Invalid number of bottles" message is displayed
  4. Select a 6-bottles package, then try to insert 7 bottles
Correct answer: C
Question 3
The following are the requirements identified as “critical”:
REQ-SEL-001. The user shall be able to combine all the three products with all the four durations to define an item to purchase 
REQ-SEL-002. The user shall be able to add a maximum of six different items to the shopping cart 
REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using a credit voucher 
REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using the available credit already charged on the smartcard 
REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using all the accepted credit cards (Visa, MasterCard and Great Wall Card) 
REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both the “select” and “purchase” pages going back to the “browse” page (anonymous navigation) 
Moreover the following quality risk item has been identified as “critical”:
QR-P1. The web customer portal might not be able to provide the expected response time (less than 10 sec) for the purchase transactions under a load of up-to 1000 concurrent users 
Test analysis for system testing has just begun and the following test conditions have been identified. 
TC-SEL-01. Test the combinations of products and durations to define an item to purchase 
TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart 
TC-PUR-01. Test the purchase of an item 
TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard 
What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and EXCR2 exit criteria?
  1. 1
  2. 2
  3. 3
  4. 4
Correct answer: C
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!