Question 1
A manufacturer produces HDMI cables. Typically, the item is manufactured.  
The manufacturer will occasionally buy unbranded HDMI cables from a vendor in order to keep up with demand. The company must use the same item number whether they make or buy the item.  
What should you do? 
  1. Select route type as vendor on the route operation when the item is to be purchased.
  2. In default order settings, select Production for the default order type
  3. Create a new vendor resource when the item is to be purchased
  4. In default order settings, select Purchase for the default order type
Correct answer: A
Question 2
A company produces paints and assembles bicycle frames.  
You must account for paint drying time before assembly operations can begin. You need to set up the operation to encompass queue times.  
Which two options can you use? Each correct answer presents part of solution.  
NOTE: Each correct selection is worth one point.
  1. Enter a value in the queue time after field for the painting operation
  2. Make a resource group for each size and color and assign that group to the operation 
  3. Enter a value in the transit time on the painting operation
  4. Enter a value in the queue time before field for the assembly operation
  5. Build capabilities for each resource related to color
Correct answer: AD
Question 3
A company manufactures automobile engines.  
You must create product configurations for values that are used in different types of engines. Each value is based on a master valve design. Different gaskets and fittings are used to allow valves to work with different engines.  
You need to translate production plans into Dynamics 365 Finance and Operations elements.  
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order. 
Correct answer: To display the answer, ProfExam Simulator is required.
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!