Question 1
Ned is the project manager for his organization. Ned is using a standard tool to capture, store, and distribute information to the stakeholders about the project costs, schedule, and performance. What term is assigned to this communication tool?
  1. Project management information system
  2. Table reporting
  3. Reporting system
  4. Communications management system
Correct answer: C
Explanation:
This is simply an example of a reporting system. It can be part of the project management information system, but for your examination, the PMBOK acknowledges this tool directly as part of project performance reporting. Reporting system is a tool and technique used for reporting performance. It is a standard means to store, capture, and give out the information to the stakeholders about the project costs, performance, and schedule.Incorrect Answers:A: The project management information system does more than just communicating the performance. It is a tool to help the project manager plan and monitor the project.B: Table reporting is one output of a reporting system, not the entire system.D: The PMBOK does not mention a communications management system.
This is simply an example of a reporting system. It can be part of the project management information system, but for your examination, the PMBOK acknowledges this tool directly as part of project performance reporting. Reporting system is a tool and technique used for reporting performance. It is a standard means to store, capture, and give out the information to the stakeholders about the project costs, performance, and schedule.
Incorrect Answers:
A: The project management information system does more than just communicating the performance. It is a tool to help the project manager plan and monitor the project.
B: Table reporting is one output of a reporting system, not the entire system.
D: The PMBOK does not mention a communications management system.
Question 2
You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?
  1. Estimate activity durations
  2. Estimate activity resources
  3. Control schedule
  4. Develop schedule
Correct answer: C
Explanation:
In severe cases, new schedule duration estimates with new forecasted start and finish dates are needed. In these instances, it is an example of using the control schedule process. Control schedule process is a method of monitoring the status of the project to update project progress and deal with the changes to the schedule baseline. It is concerned with: Determining the current status of the project Influencing the factors that create schedule changes Determining that the project schedule has changed Managing the actual changes as they occur Control schedule is a component of the Perform Integration Change Control process.Incorrect Answers:A: This is a tempting choice, but according to the PMBOK, new schedules are part of the control schedule process.B: The activity resources would only address the addition or replacement of resources needed to complete the project work.D: Develop schedule is not the best choice for this question. It is a process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
In severe cases, new schedule duration estimates with new forecasted start and finish dates are needed. In these instances, it is an example of using the control schedule process. Control schedule process is a method of monitoring the status of the project to update project progress and deal with the changes to the schedule baseline. It is concerned with: Determining the current status of the project Influencing the factors that create schedule changes Determining that the project schedule has changed Managing the actual changes as they occur Control schedule is a component of the Perform Integration Change Control process.
Incorrect Answers:
A: This is a tempting choice, but according to the PMBOK, new schedules are part of the control schedule process.
B: The activity resources would only address the addition or replacement of resources needed to complete the project work.
D: Develop schedule is not the best choice for this question. It is a process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Question 3
Which of the following individuals has a management role in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance?
  1. Functional manager
  2. Operations manager
  3. Project manager
  4. Seller
Correct answer: B
Explanation:
The role of operations manager is to perform various management roles in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance. The operations manager directly deals with constructing and maintaining the saleable products or services of the enterprise.Incorrect Answers:A: The role of a functional manager is to perform various management roles within an administrative or functional area of the business, such as human resources, finance, accounting, or procurement. He is assigned his own permanent staff to carry out the ongoing work. He should have a clear directive to manage all tasks within his functional area of responsibility.C: A project manager is an expert in the field of project management. He is responsible for the entire project from inception to completion. The project manager leads the team and helps negotiate the multiple relationships within any project whether with clients, team members, firm principals or any variety of partners and functions as the hub of a project.D: Seller is also known as a vendor, supplier or contractor. They are external company's elements that enter into a contractual agreement to provide components or services necessary for the project.
The role of operations manager is to perform various management roles in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance. The operations manager directly deals with constructing and maintaining the saleable products or services of the enterprise.
Incorrect Answers:
A: The role of a functional manager is to perform various management roles within an administrative or functional area of the business, such as human resources, finance, accounting, or procurement. He is assigned his own permanent staff to carry out the ongoing work. He should have a clear directive to manage all tasks within his functional area of responsibility.
C: A project manager is an expert in the field of project management. He is responsible for the entire project from inception to completion. The project manager leads the team and helps negotiate the multiple relationships within any project whether with clients, team members, firm principals or any variety of partners and functions as the hub of a project.
D: Seller is also known as a vendor, supplier or contractor. They are external company's elements that enter into a contractual agreement to provide components or services necessary for the project.
Question 4
Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities.
This is an example of which term?
  1. Resource calendar conflict
  2. Matrix network
  3. Organizational process assets
  4. Activity resource requirements
Correct answer: D
Explanation:
Because the activities in Beth's project require Tim and his skills. This is an example of an activity resource requirement. A resource constraint would also have been an acceptable answer.Incorrect Answers:A: A resource calendar conflict is not a valid project management term.B: This may be a matrix organization, but matrix network is not a valid project management term.C: Organizational process assets are things that have been created to help assist the management of the project.
Because the activities in Beth's project require Tim and his skills. This is an example of an activity resource requirement. A resource constraint would also have been an acceptable answer.
Incorrect Answers:
A: A resource calendar conflict is not a valid project management term.
B: This may be a matrix organization, but matrix network is not a valid project management term.
C: Organizational process assets are things that have been created to help assist the management of the project.
Question 5
John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?
  1. Work performance information
  2. Change requests
  3. Work performance measurements
  4. Forecasting method
Correct answer: D
Explanation:
Forecasting method is a technique used in generating performance reports. Forecasting is the process of estimating or predicting in unknown situations.Forecasting is about predicting the future as accurately as possible with the help of all the information available, including historical data and knowledge of any future events that might impact forecasts. The forecasting methods are categorized as follows: Time series method: It uses historical data as the basis for estimating future outcomes. Causal/econometric method: This forecasting method is based on the assumption that it is possible to identify some factors that might influence the variable that is being forecasted. If the causes are understood, projections of the influencing variables can be made and used in the forecast.Judgmental method: Judgmental forecasting methods incorporate intuitive judgments, opinions, and subjective probability estimates. Other methods: Other methods may include probabilistic forecasting, simulation, and ensemble forecasting. It is one of the tools and techniques of the report performance process.Incorrect Answers:A: Work performance information is the data gathered on the status of the project schedule activities that are performed to accomplish the project work. This data is collected as part of the Direct and Manage Project Execution processes. WPI includes the following: Deliverables status Schedule Progress Costs incurred It is used as an input in generating the report performance process.B: Change requests are requests to expand or reduce the project scope, modify policies, processes, plans, or procedures, modify costs or budgets or revise schedules. These requests for a change can be direct or indirect, externally or internally initiated, and legally or contractually imposed or optional. A ProjectManager needs to ensure that only formally documented requested changes are processed and only approved change requests are implemented. It is an output of the report performance process.C: Work performance measurements are created from the work performance information. WPMs are an output of Control schedule, Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs consist of planned versus actual performance indicators with respect to scope, schedule, and cost. They are documented and communicated to the stakeholders and are used to make project activity metrics, such as the following: Planned vs.Actual Technical performance and Scope performance Planned vs. Actual Schedule performance Planned vs. Actual Cost performance They are used as an input in generating the report performance process.
Forecasting method is a technique used in generating performance reports. Forecasting is the process of estimating or predicting in unknown situations.
Forecasting is about predicting the future as accurately as possible with the help of all the information available, including historical data and knowledge of any future events that might impact forecasts. The forecasting methods are categorized as follows: Time series method: It uses historical data as the basis for estimating future outcomes. Causal/econometric method: This forecasting method is based on the assumption that it is possible to identify some factors that might influence the variable that is being forecasted. If the causes are understood, projections of the influencing variables can be made and used in the forecast.
Judgmental method: Judgmental forecasting methods incorporate intuitive judgments, opinions, and subjective probability estimates. Other methods: Other methods may include probabilistic forecasting, simulation, and ensemble forecasting. It is one of the tools and techniques of the report performance process.
Incorrect Answers:
A: Work performance information is the data gathered on the status of the project schedule activities that are performed to accomplish the project work. This data is collected as part of the Direct and Manage Project Execution processes. WPI includes the following: Deliverables status Schedule Progress Costs incurred It is used as an input in generating the report performance process.
B: Change requests are requests to expand or reduce the project scope, modify policies, processes, plans, or procedures, modify costs or budgets or revise schedules. These requests for a change can be direct or indirect, externally or internally initiated, and legally or contractually imposed or optional. A Project
Manager needs to ensure that only formally documented requested changes are processed and only approved change requests are implemented. It is an output of the report performance process.
C: Work performance measurements are created from the work performance information. WPMs are an output of Control schedule, Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs consist of planned versus actual performance indicators with respect to scope, schedule, and cost. They are documented and communicated to the stakeholders and are used to make project activity metrics, such as the following: Planned vs.
Actual Technical performance and Scope performance Planned vs. Actual Schedule performance Planned vs. Actual Cost performance They are used as an input in generating the report performance process.
Question 6
You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special hardware to electronically lock and open the doors. You've gathered the project team before they begin the installation for a hands-on training. As a group you and the project team install 50 doors following a checklist of instructions so that every door will be installed exactly the same throughout the campus and with minimal waste. This is an example of what project execution technique?
  1. Preventive action
  2. Defect repair validation
  3. Implemented corrective action
  4. Quality control
Correct answer: A
Explanation:
This is an example of a preventive action as you're working with the team before they install the doors to train them on the installation. The checklist is a quality control tool but the question was asking for a project execution activity. Preventive and corrective actions are part of project execution.Incorrect Answers:B: The defect repair validation comes after the project team has corrected an error - something that has not occurred in this instance.C: Corrective action is a response to something that needs to be corrected in the project.D: Quality control is a controlling and monitoring process, not an executing process.
This is an example of a preventive action as you're working with the team before they install the doors to train them on the installation. The checklist is a quality control tool but the question was asking for a project execution activity. Preventive and corrective actions are part of project execution.
Incorrect Answers:
B: The defect repair validation comes after the project team has corrected an error - something that has not occurred in this instance.
C: Corrective action is a response to something that needs to be corrected in the project.
D: Quality control is a controlling and monitoring process, not an executing process.
Question 7
You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?
  1. It means the largest schedule variance you can have is five percent.
  2. It is the earned value divided by the planned value for your project.
  3. It is the expectation of management to be 95 on schedule at 95 percent of the project.
  4. It means you will need to earn at least 95 cents per dollar invested in the project.
Correct answer: A
Explanation:
Conformance to schedule is a required adherence for the project's schedule. In this instance, the project manager must not allow the schedule to slip more than five percent.Incorrect Answers:B: This is the description of the schedule performance index.C: This is not a valid statement about the project performance.D: This is the description of the cost performance index.
Conformance to schedule is a required adherence for the project's schedule. In this instance, the project manager must not allow the schedule to slip more than five percent.
Incorrect Answers:
B: This is the description of the schedule performance index.
C: This is not a valid statement about the project performance.
D: This is the description of the cost performance index.
Question 8
Examine the figure given below:
If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?
  1. Three days
  2. One day
  3. Four days
  4. Zero days
Correct answer: B
Explanation:
Activity B is not on the critical path and it has a total of four days of float. If Activity B takes a total of eight days, it will consume three days of float. However, the total duration of the path ABEHJ may not exceed 26 days, as this is the total duration for the project. Although Activity H has a total of four days of float available, the consumption of three days of float on this path will reduce the total float for Activity H to just one day. If Activity H is delayed by more than one day, then the project will be late.Incorrect Answers:A, C: These are not the valid answers, as there is just one day of float available for Activity H.D: There is one day of float still available for Activity H.
Activity B is not on the critical path and it has a total of four days of float. If Activity B takes a total of eight days, it will consume three days of float. However, the total duration of the path ABEHJ may not exceed 26 days, as this is the total duration for the project. Although Activity H has a total of four days of float available, the consumption of three days of float on this path will reduce the total float for Activity H to just one day. If Activity H is delayed by more than one day, then the project will be late.
Incorrect Answers:
A, C: These are not the valid answers, as there is just one day of float available for Activity H.
D: There is one day of float still available for Activity H.
Question 9
You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?
  1. A significant point in the project
  2. A goal of reaching a significant delivery of project benefits by an identified date
  3. An imposed date for the project to reach a given point
  4. The completion of a project activity that is crucial to project completion
Correct answer: A
Explanation:
A milestone is simply a significant point or event in the project. It does not have to be assigned to a specific date, but is usually assigned to the completion of project phases. A milestone is the end of a stage that marks the completion of a work package or phase, typically marked by a high level event such as completion, endorsement or signing of a deliverable, document or a high level review meeting. In addition to signaling the completion of a key deliverable, a milestone may also signify an important decision or the derivation of a critical piece of information, which outlines or affects the future of a project. In this sense, a milestone not only signifies distance traveled (key stages in a project) but also indicates direction of travel since key decisions made at milestones may alter the route through the project plan. To create a milestone, enter 0 (zero) in the Duration field. The task will automatically be classified as a milestone.Incorrect Answers:B: A project goal is an objective for time, cost, scope, and other metrics.C: This is a project constraint.D: All activities must be completed in order to complete the project work. Activities that are not completed are quality issues that prevent the project from completing the project scope.
A milestone is simply a significant point or event in the project. It does not have to be assigned to a specific date, but is usually assigned to the completion of project phases. A milestone is the end of a stage that marks the completion of a work package or phase, typically marked by a high level event such as completion, endorsement or signing of a deliverable, document or a high level review meeting. In addition to signaling the completion of a key deliverable, a milestone may also signify an important decision or the derivation of a critical piece of information, which outlines or affects the future of a project. In this sense, a milestone not only signifies distance traveled (key stages in a project) but also indicates direction of travel since key decisions made at milestones may alter the route through the project plan. To create a milestone, enter 0 (zero) in the Duration field. The task will automatically be classified as a milestone.
Incorrect Answers:
B: A project goal is an objective for time, cost, scope, and other metrics.
C: This is a project constraint.
D: All activities must be completed in order to complete the project work. Activities that are not completed are quality issues that prevent the project from completing the project scope.
Question 10
You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for all future organizational projects based on your project's performance, approach, and implementation of project processes. All of the following should be included in your project's process improvement plan except for which one?
  1. Process boundaries
  2. Process configuration
  3. Targets for improved performance
  4. Identification of project risks
Correct answer: D
Explanation:
Identification of the project risks is not part of the process improvement plan. Identify risks is a risk management process, and risks are recorded in the risk register.Incorrect Answers:A, B, C: Process boundaries, Process configuration and Targets for improved performance are parts of the process improvement plan.
Identification of the project risks is not part of the process improvement plan. Identify risks is a risk management process, and risks are recorded in the risk register.
Incorrect Answers:
A, B, C: Process boundaries, Process configuration and Targets for improved performance are parts of the process improvement plan.
Question 11
Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
  1. Precedence Diagramming Method
  2. Schedule network template
  3. Dependency determination
  4. Activity on the Node
Correct answer: A
Explanation:
The Precedence Diagramming Method uses both predecessors and successors as nodes in the project network diagram. The PDM approach is the most common network diagram approach used.Incorrect Answers:B: The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram.C: Dependency determination identifies the order of the project work.D: Activity on the node places activities on circles within a network diagram. It is an example of the precedence diagramming method.
The Precedence Diagramming Method uses both predecessors and successors as nodes in the project network diagram. The PDM approach is the most common network diagram approach used.
Incorrect Answers:
B: The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram.
C: Dependency determination identifies the order of the project work.
D: Activity on the node places activities on circles within a network diagram. It is an example of the precedence diagramming method.
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX FILES