Question 1
In Project Cost Management, which input is exclusive to the Determine Budget process?
  1. Scope baseline
  2. Organizational process assets
  3. Project schedule
  4. Resource calendars
Correct answer: D
Question 2
The key benefit of the Monitoring and Controlling Process Group is the ability to:
  1. establish and manage project communication channels, both external and internal to the project team.
  2. influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.
  3. monitor the ongoing project team against the team performance assessments and the project performance baseline.
  4. observe and measure project performance regularly and consistently to identify variances from the project management plan.
Correct answer: D
Question 3
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
  1. Project Plan
  2. Responsibility Matrix
  3. Issue Log
  4. Scope Document
Correct answer: C
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!