Question 1
MANAGING A STAGE BOUNDARY 
The ABC Company trainers have been accredited and the course booking procedures have been amended. The ‘managing a stage boundary’ process is taking place at the end of stage 3. 
Which activity should occur during the ‘update the business case’ activity?
  1. Update the overall plan with the time and cost taken to develop the ‘e-learning course’ and ‘amended course booking procedures’
  2. Break the ‘planned pilot courses’ down into component products in order to identify the work required to deliver them.
  3. Review whether the possible sales of the training course to external companies are likely to cover the project costs.
  4. Review whether a new team manager should be appointed to lead the delivery of the pilot courses during stage 4.
Correct answer: A
Question 2
Based on lessons from previous projects that used the ABC Company standard development model, the project board has set low cost and time tolerances for stage 2. As a result, the project manager plans to set very low tolerances for time and cost for all work packages to be carried out during stage 2. 
Is this an appropriate application of the ‘manage by exception’ principle, and why?
  1. Yes, because the project manager should set tolerance equally for all work packages in a stage.
  2. Yes, because setting appropriate tolerances for work packages will help keep the stage within tolerances.
  3. No, because tolerances set by the project manager should be the same as those set by the project board.
  4. No, because the project manager should divide the stage tolerances between the team managers.
Correct answer: B
Question 3
During stage 4, a work package was authorized for the ‘delivered pilot courses’ to be completed by the end of week 2. The ‘finalized materials’ work package will start in week 3. Both work packages have zero tolerances, and finalizing the materials is dependent on feedback from the pilot courses. 
During week 1, there were some problems with the pilot courses, so at the start of week 2 the team manager rescheduled the courses to week 3, and reported this in the weekly checkpoint report as the end of week 2. 
Should the team manager have reported this delay previously as an issue, and why?
  1. Yes, because the work package to deliver the pilot courses was forecast to exceed its time tolerance.
  2. Yes, because a team manager should not change the scheduled order of a work package.
  3. No, because the checkpoint report for week 1 should include information on any issues that occurred.
  4. No, because the feedback from the rescheduled courses can be used in week 4 to finalize the materials.
Correct answer: C
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!