Question 1
A Scrum Team has been working on a product for 9 Sprints. A new Product Owner who is new to Scrum joins the team and understands she is accountable for the Product Backlog. However, she is unsure about the purpose of the Product Backlog. She has read that the Product Backlog should be a list of all user features for the product. She goes to the Scrum Master asking where to put the other types of requirements that are going to be taken into account. Are all of the following types of requirements acceptable on a Product Backlog? Stability requirements. Performance requirements. Product Functionality. Documentation. Fixes. (choose the best answer)
  1. Yes, they all belong on the Product Backlog. Product Backlog is supposed to be the Single Source of Truth for all the work for the product.
  2. No, Product Backlog is a tool for the Product Owner. The Product Owner represents the users and stakeholders. Other types of requirements should be managed separately by the Developers. They are not the Product Owner's concern.
Correct answer: A
Question 2
What variables should a Product Owner consider when ordering the Product Backlog? (choose the best answer)
  1. Development cohesion as indicated by the Developers.
  2. The availability of resources and skills for implementation.
  3. Lowest development cost in order to maximize Return on Investment (ROI).
  4. Effort first, then value.
  5. Anything that informs them to achieve the product's goals and to optimize the value delivered.
Correct answer: E
Question 3
It is mandatory for the Product Owner to monitor and share progress of the Product Backlog by using which method? (choose the best answer)
  1. A Product or Release burn-down chart.
  2. A Value burn-up chart.
  3. A Gantt Chart.
  4. Any practice based on trends of work completed and upcoming work.
  5. A Sprint Review acceptance report.
Correct answer: D
Question 4
The Product Owner manages the Product Backlog. Who is accountable for estimating the effort to complete the Product Backlog Items? (choose the best answer)
  1. The Developers.
  2. The PMO.
  3. The Product Owner.
Correct answer: A
Question 5
True or False: The Sprint Review is the only time at which stakeholder feedback is taken into account.
  1. True.
  2. False.
Correct answer: B
Question 6
How do timeboxes help the Product Owner and the other members of the Scrum Team validate assumptions, adapt, and maximize the value of their product? (choose the best answer)
  1. Timeboxes help by making sure a Sprint does not stop until all testing is done, and the work is verified by the Product Owner.
  2. Timeboxes assure the Product Owner that the Developers will finish all work on the Sprint Backlog by the end of the Sprint.
  3. Timeboxes help minimize risk by creating the opportunity to validate assumptions using feedback from users and the market; allowing Scrum Teams to inspect progress toward the Product Goal and decide whether to pivot or persevere.
  4. At the end of each Sprint when the timebox expires a detailed report with all test cases and test results is available.
Correct answer: C
Question 7
True or False: The value delivered by a product can only be determined by revenue.
  1. True.
  2. False.
Correct answer: B
Question 8
True or False: The Scrum Team must choose at least one high priority process improvement item, identified during the Sprint Retrospective, and place it in the Sprint Backlog.
  1. True.
  2. False.
Correct answer: B
Question 9
How important is it for a Product Owner to order Product Backlog Items by using value points? (choose the best answer)
  1. Calculating value points is a predictive approach that conflicts with the empiricism of Scrum, and is therefore not acceptable.
  2. Using value points is the ultimate way for a Product Owner to predict the value that the product will provide.
  3. The Product Owner may order the Product Backlog by using value points or select another technique, the decision is up to them.
Correct answer: C
Question 10
When can the Product Backlog be updated? (choose the best answer)
  1. Never, unless agreed to by the change request.
  2. At any time when done by the Product Owner or a delegate.
  3. Only after a Sprint Review if agreed to by the stakeholders.
  4. Only during Product Backlog Refinement sessions if the Product Owner is present.
Correct answer: B
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!