Question 1
Scenario: Rollins Manufacturing 
Please read this scenario prior to answering the question 
Rollins Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own Manufacturing Requirements Planning (MRPII) system, production scheduling, and custom developed applications that drive the automated production equipment at each plant. 
Rollins is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current MRPII and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff. 
The Rollins Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation. 
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their MRPII and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed. 
Refer to the Rollins Manufacturing Scenario 
You are serving as the Lead Enterprise Architect for the Common ERP Deployment architecture project. 
One of the earliest initiatives in the Enterprise Architecture program at Rollins was the definition of a set of IT principles and architecture principles that are well aligned with the overall enterprise principles. These now need to be updated to address the concerns raised. 
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution. 
[Note: You should assume that Rollins has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.]
Based on TOGAF 9, which of the following is the best answer?
  1. Common-use Applications, Data is Shared, Data is Accessible, Data is Secure, Interoperability, Control Technical Diversity.
  2. Business Continuity, Service-orientation, Data is Accessible, Data is Secure, Responsive Change Management.
  3. Maximize Benefit to the Enterprise, Business Continuity, Common-use Applications, Data is Shared, Data is Accessible, Data is Secure.
  4. Information Management is Everybody's Business, IT Responsibility, Data Trustee, Technology Independence, Responsive Change Management.
Correct answer: C
Question 2
Scenario: Global Mobile 1
Please read this scenario prior to answering the question 
Global Mobile is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer. 
Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average. The Corporate Marketing group has published some new findings about customer satisfaction. The customers appear to be switching to Air Light, a competitor, because of superior customer service. Global Mobile actually has better coverage in nearly all markets than Air Light, and good roaming agreements that keep rates low for business travelers. But, customer satisfaction has remained low. 
The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan. They have developed a business scenario which contains a good conceptual model of what needs to be done, and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board. 
The planning for the program has been underway for several months. Global Mobile has selected TOGAF 9 as the basis for its Enterprise Architecture. 
The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation. The Corporate Board has placed one additional major constraint on the program. In addition to achieving the business outcomes directly related to improving overall customer service within each business unit, the Corporate Board expects the Target Architecture to produce an additional saving of at least 30% over current operating costs through energy efficiency initiatives, virtualization of servers and workstations, and expanded telecommuting and desk-sharing. This Green initiative is intended to become a model for future investments at all company facilities worldwide. 
Refer to Global Mobile scenario 
You have been engaged as a consultant to advise the Chief Architect on the best ways to approach to the implementation planning activities for this significant business transformation. 
Based on TOGAF 9, which of the following is the best answer? (Is this the right answers to choose?)
  1. You recommend using conventional implementation planning techniques. The horizontal scope of the Green initiative would make the Capability-Based Planning approach used in the organization's TOGAF-based Enterprise Architecture framework difficult to manage and govern. This approach to planning was better applied within the vertical scope of a business unit.
  2. You recommend that the implementation planning activities be conducted using Capability-Based Planning. This is appropriate because the Green initiative is an enterprise-wide plan with a horizontal scope. Its metrics are aggregated at the enterprise level. It is crucial to gain business unit support and cooperation to achieve the broader business outcomes which will benefit all.
  3. The Capability-Based Planning approach used in the organization's TOGAF-based Enterprise Architecture framework is focused on business outcomes. The Green initiative is an infrastructure program that is technical in nature; therefore, it would not be appropriate to use the Capability-Based Planning approach. Instead, the Global Mobile systems development lifecycle approach should be utilized to develop the Solution Architecture.
  4. You recommend using conventional implementation planning techniques. The Capability-Based Planning approach is normally only used in public sector, defense-related programs. This approach is not appropriate for a private sector company.
Correct answer: B
Question 3
Scenario: Vittronics Ltd.
Please read this scenario prior to answering the question 
Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache. 
This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets. 
The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to create a Secure Private Immersive Collaborative Environment (SPICE) that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials. 
The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. They have recently upgraded to TOGAF 9. The Vittronics Architecture Development Method (VADM) is strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support current good manufacturing practices and good laboratory practices in their target markets. 
The SPICE project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed in SPICE, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding SPICE Security Architecture has been defined. 
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. 
Refer to the Vittronics Ltd Scenario 
You are serving as the Lead Architect for the SPICE project team. 
As required by TOGAF, the SPICE project team res completed a Business Transformation Readiness Assessment in Phase A (Architecture Vision). In that assessment, it was determined that there are risks associated with the adoption of the Immersive Collaborative Environment. Despite a clear expression of the vision and the business need for utilizing SPICE to accelerate the clinical trials, the researchers have been resisting the change because of concerns about safeguarding individually identifiable information about the subjects who were participating in the trials. 
You have been asked to recommend how this situation be managed in the implementation planning phases. 
Based on TOGAF 9, which of the following is the best answer?
  1. You decide that in Phase E, the team creates an overall solutions strategy that can guide the Target Architecture implementation and structure the Transition Architectures. You check that there is consensus before proceeding.
  2. You decide to return to Phase A, where the team should brainstorm a technical solution that mitigates the residual risks presented by the privacy issue. Then, during Phase D, you will direct the team to develop an Architecture Building Block to manage the security risks. After that, the team should select Solution Building Blocks that mitigate all of the identified risks and revise the Requirements Impact Statement to reflect the changes to the high-level solutions strategy and migration plan.
  3. You decide that in Phase E, the team review the Business Transformation Readiness Assessment and identify, classify, and mitigate the risks associated with the identified readiness factors. If the risks can be satisfactorily mitigated, then you would continue to define a high-level solutions strategy that includes the Transition Architectures needed to make the change culturally and technically feasible.
  4. You decide that in Phase E, the team determines an approach to implementing an overall strategic direction that will address and mitigate the risks identified.
Correct answer: B
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!